Pre-Monsoon Drain Desilting Works Accelerated Across Bengaluru East
Bengaluru East City Corporation Commissioner D.S. Ramesh inspected ongoing pre monsoon infrastructure and storm water drain maintenance works across multiple areas and directed officials to speed up desilting and complete pending works befo…
Namma Ward Editorial TeamMay 8, 20260 viewsnammaward.in

Bengaluru East City Corporation Commissioner D.S. Ramesh inspected ongoing pre-monsoon infrastructure and storm water drain maintenance works across multiple areas and directed officials to speed up desilting and complete pending works before the monsoon season.



Key Details:
- Commissioner D.S. Ramesh inspected railway vent works at Geddalahalli.
- One concrete box pushing work has been completed as planned.
- Officials were instructed to complete remaining works before May 30, 2026.
- Storm water drain desilting and cleaning works were reviewed in:
Vignananagara
- Ramamurthy Nagara
- Kalkere
- Directions were issued to remove silt, debris, mud, and vegetation from drains on priority.
- Officials were instructed to ensure uninterrupted connectivity between primary, secondary, and tertiary drains.
- The Corporation directed strict action against dumping waste into storm water drains and roadside drains.
- Additional monitoring and marshals will be deployed at identified black spots to prevent waste accumulation.
- Safety precautions at work sites were also emphasized to avoid inconvenience to the public.