Inspection by Chief Commissioner Maheshwar Rao in West City Corporation; Push for Online Registers and Road Infrastructure Upgrades
Chief Commissioner Maheshwar Rao inspected multiple civic works and administrative systems within the Bengaluru West City Corporation jurisdiction.

Chief Commissioner Maheshwar Rao inspected multiple civic works and administrative systems within the Bengaluru West City Corporation jurisdiction. During the visit, he directed officials to digitize manual register systems from the upcoming financial year and reviewed ongoing infrastructure and traffic improvement works across several locations.





Key Details
- Authority: Greater Bengaluru Authority (GBA)
- Inspection Area: Bengaluru West City Corporation jurisdiction
- Lead Official: Chief Commissioner Maheshwar Rao
Administrative System Upgrade
- Officials were instructed to upgrade manual register systems to an online system starting from the next financial year.
- The directive came during inspection of job code and technical approval registers at the RR Nagar Zonal Office.




RR Nagar Zonal Office Improvements
- Additional office spaces are being constructed on the third floor of the zonal office building.
- Officials were directed to complete the construction work at the earliest.
- Instructions were issued to:
Maintain cleanliness inside the office premises
- Ensure well-organized surroundings
- Renovate and upgrade the meeting hall
- Remove storage boxes placed in corridors
Development of Shankar Mutt Circle
- Inspection of asphalting work on Shankar Mutt Road in Mahalakshmi Layout.
- Officials were instructed to:
Provide a free left turn from Modi Hospital Road to Basaveshwara Main Road
- Provide a free left turn from Kurubarahalli Road to Shankar Mutt Road
- Prepare a design plan through urban planners for the comprehensive development of Shankar Mutt Circle.
Dr. Rajkumar Road White Topping Work
- Inspection of white topping road work on Dr. Rajkumar Road.
Progress Update:
- 700-metre stretch between Navrang Theatre and Rajajinagar 10th Cross:
One section completed and opened to traffic.
- Remaining portion expected to be completed by March 31.
- 1.8 km stretch from Navrang to Star Bazaar Signal:
Utility works on one side completed.
- White topping work to begin immediately.
- Officials instructed to complete one side by the end of July.
Traffic Improvement Proposal
- Kurubarahalli Main Road identified as a narrow corridor causing congestion.
- Officials were instructed to examine the feasibility of road widening and submit a report.
Other Observations During Inspection
- Proposal for leaf processing unit installation at Nagapura Pipeline Park
- Visit to Nagapura Phase-II collection and transportation centre with instructions to upgrade it into a well-equipped facility
- Direction to expedite white topping work on Mahalakshmi Layout Main Road
- Instruction to procure a jet patcher machine immediately for pothole repairs in West City Corporation areas
Important Dates / Deadlines
- Online register system implementation: Next Financial Year
- Dr. Rajkumar Road remaining stretch completion target: March 31
- White topping (Navrang to Star Bazaar stretch – one side): End of July