GBA Directs Completion of Stormwater Drain Works Before Monsoon
The Greater Bengaluru Authority (GBA) has instructed officials to complete ongoing stormwater drain (rajakaluve) development works before the monsoon, with a focus on lake connectivity and nature based solutions.

The Greater Bengaluru Authority (GBA) has instructed officials to complete ongoing stormwater drain (rajakaluve) development works before the monsoon, with a focus on lake connectivity and nature-based solutions.

Key Details:
- Directed by: Maheshwar Rao, Chief Commissioner, GBA
- Objective: Complete stormwater drain works before pre-monsoon rains (May)
- Focus: Flood prevention, lake rejuvenation, and sustainable infrastructure
Project Funding:
- ₹175 crore under National Disaster Mitigation Fund (NDMF)
- ₹2000 crore under World Bank-assisted Karnataka Water Security and Resilience Programme (KWSRP)
Key Instructions:
- Expedite stormwater drain works connecting one lake to another
- Ensure completion before onset of monsoon
- Prioritize nature-based solutions in all projects
Nature-Based Approach:
- Prevent sewage entry into lakes
- Replicate wetland model (Jakkur Lake) across other lakes
- Use plants like Colocasia and Canna indica for natural filtration
Location-Specific Updates:
- Srinivasapura Lake to Kogilu Lake (1.1 km):
Wetland development to be strengthened
- Sluice gate installation at Kogilu Lake before monsoon
- Srinivasapura Lake:
Rejuvenation works to be taken up on priority
- Bellahalli Lake to Kannur Lake (660 m):
New drain under construction to address flooding
- Kannur Village:
470 m RCC retaining wall work in progress
- Chokkanahalli Lake to Agrahara Lake (670 m):
Drain construction underway with temporary diversion
- Rachenahalli Main Road (600 m):
Drain work progressing rapidly
- Nagawara Junction:
Drain construction along road planned to prevent waterlogging
- Dasarahalli Main Road:
Buffer zone along drain to be developed into pedestrian-friendly public space