Expedite Hulimavu Lake Development Work, Directs Special Commissioner Sushma Godbole
The Special Commissioner of the FECC Division of the Greater Bengaluru Authority (GBA), Sushma Godbole , inspected Hulimavu Lake and directed officials to accelerate ongoing development works, complete the sewage treatment plant, and preven…

The Special Commissioner of the FECC Division of the Greater Bengaluru Authority (GBA), Sushma Godbole, inspected Hulimavu Lake and directed officials to accelerate ongoing development works, complete the sewage treatment plant, and prevent sewage discharge into the lake. She also reviewed flood-prone areas around Arekere Lake and instructed departments to take precautionary measures ahead of the monsoon.



Key Details:
- Sushma Godbole visited Hulimavu Lake under Bengaluru South City Corporation.
- Residents raised concerns regarding delays in lake development works, which have been underway since 2022.
- Complaints were made about sewage water entering the lake and polluting the water body.
- The Special Commissioner instructed BWSSB officials to speed up the construction of the Sewage Treatment Plant (STP).
- BWSSB was directed to ensure sewage water does not enter the lake and to create suitable barriers.
- Officials were instructed to install wire fencing around the lake to prevent encroachments and improve safety.
- A public information board displaying details of ongoing works has been ordered to be installed at the site.
- Flood-prone areas around Arekere Lake were inspected following recent rains.
- Officials were directed to undertake precautionary measures to avoid flooding during the monsoon season.
- Immediate shifting of optical fibre cables and BESCOM electricity lines obstructing road and stormwater drain (Rajakaluve) works was also ordered.