The Greater Bengaluru Development Department , Government of Karnataka , has reported significant progress under the Safe Footpath Campaign .
Namma Ward Editorial TeamJuly 7, 20260 viewsnammaward.in

The Greater Bengaluru Development Department, Government of Karnataka, has reported significant progress under the Safe Footpath Campaign. Over a three-day drive from July 1 to July 3, encroachments were cleared from 202.70 km of footpaths along arterial and sub-arterial roads across the five Bengaluru City Corporations under the Greater Bengaluru Authority (GBA).
Key Details:
- Campaign: Safe Footpath Campaign
- Duration: July 1–3
- Total Footpaths Cleared: 202.70 km
Progress on July 1
- Bengaluru East City Corporation: 13.25 km
- Bengaluru Central City Corporation: 16.35 km
- Bengaluru North City Corporation: 12.85 km
- Bengaluru South City Corporation: 11.00 km
- Bengaluru West City Corporation: 23.10 km
- Total: 76.55 km
Progress on July 2
- Bengaluru East City Corporation: 8.80 km
- Bengaluru Central City Corporation: 8.55 km
- Bengaluru North City Corporation: 12.70 km
- Bengaluru South City Corporation: 10.40 km
- Bengaluru West City Corporation: 24.10 km
- Total: 64.55 km
Progress on July 3
- Bengaluru East City Corporation: 8.55 km
- Bengaluru Central City Corporation: 10.95 km
- Bengaluru North City Corporation: 14.10 km
- Bengaluru South City Corporation: 11.50 km
- Bengaluru West City Corporation: 16.50 km
- Total: 61.60 km
Overall Progress
- July 1: 76.55 km
- July 2: 64.55 km
- July 3: 61.60 km
- Grand Total: 202.70 km